No more daily lane closures for paving; the paving for the new westbound lane (the 4th lane) is now complete. The guardrail installation for this new lane (from C & J Gravel west) will be completed over the next two weeks. The lane should be opened for travel by the end of July. (The outside westbound lane will remain closed east of C & J Gravel, however, as crews continue work on two bridge structures.) See below for regular traffic impacts.

NIGHTTIME WORK: No nighttime lane closures are scheduled until a date is set for removal of the remaining bridge false work (support structures).
 
PROJECT INFORMATION
SEMA Construction, Inc. is constructing a project for the Colorado Department of Transportation to widen US 160 through Grandview, east of Durango. Additionally we are constructing the first phase of a new interchange including building four (4) bridges and ramps. The total cost of this project is $34.4 million.
 
ANTICIPATED UPCOMING CONSTRUCTION ACTIVITIES
 
Earthwork for eastbound Ramp A, South side of HWY 160: Continues
Paving on HWY 160: Continues
False work removal on the US 160 Overpass
Bridge construction on Ramp A and Ramp C
Storm Drainage installation throughout project
 
 
REGULAR TRAFFIC IMPACTS
 
SEMA Construction and CDOT strive to have minimal effects on daily traffic but minor delays should be expected at times.  Operations will be scheduled to minimize impact during peak rush hours. Please allow extra time to reach your destination.  Lane closures/restrictions on HWY 160 between Farmington Hill and Grandview may be as follows:
 
Night time closures of US 160 for steel structure removal to be rescheduled.
Daytime traffic may be reduced to one lane in each direction between the hours of 8:00am and 3:00pm.
Nighttime traffic may be reduced to one lane in each direction between the hours of 6:30pm and 6:30am.
 
The following information will be helpful in reaching your destination:
 
Obey construction signing, lane closures and traffic control for the safety of yourself and construction personnel in the work zones.
Contact the project information line or web site below for updates.
 
MORE INFORMATION
Project Information Line 970-903-3999
Road Condition and Traveler Information:
www.cotrip.org
Email: SEMA Project Information Manager at [email protected]