US 160 Grandview 4th Lane and Interchange Update
Fourth lane to open this July; two more project phases will complete interchange by late 2011.
INTERCHANGE WILL MEET FUTURE TRAFFIC & SAFETY NEEDS: A fully-functional US 160 interchange will be completed by late 2011. The interchange may or may not include a connection with US 550 in the future—that connection point will be determined via a reevaluation process in coordination with the Federal Highway Administration. This process could take up to two years.
This interchange is one of three grade-separated (unsignalized) interchanges selected in the 2006 Record of Decision to meet future safety and capacity needs on US 160 through
INTERCHANGE CONSTRUCTION & COSTS: The current phase of interchange and highway widening work was contracted to SEMA Construction for $26.7 million (the total project cost is $34.4 million). Included in this project cost are the construction and paving of a fourth lane (2/3 of a mile long), four interchange bridges, six highway retaining walls, sub-structure work for two interchange ramps, earthwork for a 2,020-linear foot shared-use path, path retaining walls, a new signal at Farmington Hill, highway lighting, landscaping enhancements, wetlands mitigation, drainage improvements traffic control, signing and striping. (The total cost of the main overpass bridge is $6 million, including design and construction.)
Two more project phases will complete a functional US 160 interchange in this location, which is approximately one-half mile east of Farmington Hill. The interchange will have independent utility without a US 550 connection, accommodating future growth and projected traffic volumes, facilitating east-west travel and providing safe and direct access to current and future development north and south of US 160.
With phase I underway, phase II is scheduled to begin in the fall of 2009 and will include construction of an eastbound off-ramp (Ramp B) and ramp work on the north side of the highway. Phase II—which will be advertised to prospective contractors this summer—will be completed with $4 million in funding from the American Recovery and Reinvestment Act. Phase III will begin in 2011 and complete the interchange with bridge tie-ins, roundabout construction and paving. This final phase has a budget of $15 million, from state and federal funds, for an interchange project total of about $54.5 million.
CURRENT WORK AND TRAFFIC IMPACTS:
Lane closures/restrictions on HWY 160 between Farmington Hill and
- This month crews will remove the steel false-work from under the new overpass bridge. For safety, this work will require up to four consecutive nighttime closures of US 160. Closures will be from 9 p.m. to 5 a.m. More information will be provided as the dates are known.
- Crews will also be painting bridges and retaining walls.
- The fourth lane will be opened to traffic by this August.
- Daytime traffic may be reduced to one lane in each direction between 8 a.m. and 3 p.m.
- Nighttime traffic may be reduced to one lane in each direction between 6:30 p.m. and 6:30 a.m.
For further information regarding the Phase 1 construction, call the Project Information Line, 970.903.3999, or email the SEMA Project Information Manager at [email protected]. Additional updates and maps are also available at www.dot.state.co.us/us160/durango, and for information on other CDOT projects statewide, the public may log on to www.cotrip.org or call 511 from anywhere in the state.
# # #
”